 Our new multi-use sports pavilion which will be available for private hire and home to Shrivenham Cricket Club.

It will be sympathetically constructed to compliment the arts and crafts style of the Memorial Hall. 

Updated - 05/09/21

.

birds eye_edited.jpg

Updated - 05/09/21

The tiling is now taking place on the roof. Target completion date remains in December.

.

Updated - 23/08/21

This week the final stages of the roof structures are going up before it is tiled.

Image_edited.jpg

Updated - 13/08/21

.

Pavilion

Updated - 1/08/21

This week the roof structures are going up.

IMG_4090_edited.jpg

Updated - 22/07/21

This week the rafters are being installed.

RAFTERS

Updated 06/07/21

The stonework is well underway on the Pavilion, Target completion date remains December of 2021. 

Updated - 08/06/21

The Brickwork has begun on the Pavilion! 

Below is a drone image of the site taken by Neil Maw. 

Updated - 05/05/21

The footings have been dug and Concrete foundations are now being laid.

Updated - 30/04/21

Construction of the Pavilion is underway!

Below we can see PJE Contractors Ltd. breaking ground on site for the first time. 

BREAKING GROUND