top of page

PAVILION CONSTRUCTION
GALLERY AND INFORMATION

 Our new multi-use sports pavilion which will be available for private hire and home to Shrivenham Cricket Club.

It will be sympathetically constructed to compliment the arts and crafts style of the Memorial Hall. 

Updated - 05/04/22

.

__edited.jpg

Updated - 15/01/22

The Paving is currently being laid.

Paving

Updated - 18/01/22

The service trenches are being dug and services installed. 

.

Updated - 14/01/22

The plastering on the roof is now complete.

.

Updated - 5/01/22

Due to unforeseen delays we expect the new estimated completion date to be late February /early March.

Memorial Hall.jpg

Updated - 09/11/21

The windows and doors have arrived and been fitted!

IMG_5181_edited.jpg

Updated - 28/10/21

Insulation has been put in. First glimpse of the inside!

IMG_5086.JPG

Updated - 22/10/21

The scaffolding has been removed! 

IMG_5044_edited.jpg

Updated - 15/10/21

Still waiting on the arrival of the glass doors.  

.

Updated - 12/10/21

Roof tiling is now complete! 

.

Updated - 8/10/21

Unfortunately we are running a few weeks behind due to on going shortages of HGV drivers to deliver materials. However they are still making good progress with what they can do!

.

Updated - 20/09/21

The front roof tiling is now completed. 

.

Updated - 05/09/21

.

.

Updated - 05/09/21

The tiling is now taking place on the roof. Target completion date remains in December.

.

Updated - 23/08/21

This week the final stages of the roof structures are going up before it is tiled.

Image_edited.jpg

Updated - 13/08/21

.

Pavilion

Updated - 1/08/21

This week the roof structures are going up.

IMG_4090_edited.jpg

Updated - 22/07/21

This week the rafters are being installed.

RAFTERS

Updated 06/07/21

The stonework is well underway on the Pavilion, Target completion date remains December of 2021. 

STONEWORK

Updated - 08/06/21

The Brickwork has begun on the Pavilion! 

Below is a drone image of the site taken by Neil Maw. 

BLOCKWORK

Updated - 05/05/21

The footings have been dug and Concrete foundations are now being laid.

CONCRETE

Updated - 30/04/21

Construction of the Pavilion is underway!

Below we can see PJE Contractors Ltd. breaking ground on site for the first time. 

BREAKING GROUND
bottom of page